News from the sites

Sheet G-03

10 entries

Structure

Horizont

Tenth-floor slab poured.

  1. Lipa ParkFinishing works

    Plaster and screeds on all floors, courtyard landscaping begins.

  2. Brick YardFoundations

    Excavation complete, foundation slab reinforcement under way.

  3. Lipa ParkFacade and windows

    Windows fitted and facade insulation complete.

  4. Brick YardBuilding permit

    Building permit issued.

  5. HorizontFoundations

    Three basement levels complete.

  6. Lipa ParkStructure

    Structure topped out on both entrances.

  7. HorizontBuilding permit

    Building permit issued.

  8. Lipa ParkFoundations

    Foundation slab and basement level poured.

  9. Lipa ParkBuilding permit

    Building permit issued.